System design verification of a hybrid geothermal/coal fired power plant [electronic resource].
- Published:
- Oak Ridge, Tenn. : Distributed by the Office of Scientific and Technical Information, U.S. Dept. of Energy, 1978.
- Physical Description:
- Pages: 222 : digital, PDF file
- Additional Creators:
- United States. Department of Energy. Office of Scientific and Technical Information
Access Online
- Restrictions on Access:
- Free-to-read Unrestricted online access
- Summary:
- This hybrid plant utilizes geothermal fluid for feedwater heating. With respect to the extraction of available work from the geothermal fluids, this cycle is approximately two times as efficient as the all geothermal plant. The System Design Verification Study presented verifies the technical and economic feasibility of the hybrid plant. This report is comprised of a conceptual design, cost estimate, and economic analysis of a one-unit 715 MW hybrid geothermal/coal fired power plant. In addition to the use of geothermal fluid for feedwater heating, its use is also investigated for additional power generation, condensate and cooling tower makeup water, coal beneficiation, air preheating, flue gas reheating and plant space heating requirements. An engineering and construction schedule for the hybrid plant is also included.
- Report Numbers:
- E 1.99:san-1572-t2
san-1572-t2 - Subject(s):
- Other Subject(s):
- Note:
- Published through SciTech Connect.
09/01/1978.
"san-1572-t2"
Parsons (Ralph M.) Co., Pasadena, CA (USA) - Funding Information:
- EG-77-G-03-1572
View MARC record | catkey: 14153764